Wentx
Client:
China State Construction Engineering (HK) Ltd.
Description:
Wentx - R.C. Structure Works of Bioreactor & Services Building and Foundation of LTP
Category of work:
RC works
Commencement date:
Dec 2024
Expected completion date:
Jul 2025
Contract value:
HKD 84,999,777

Contract 1201
Client:
Bouygues – Dragages JV
Description:
Tung Chung Line Extension – Tung Chung West Station and Tunnels
Category of work:
RC works
Commencement date:
Jan 2025
Expected completion date:
Aug 2025
Contract value:
Approx. HKD 27,000,000

Tung Chung Extension
Client:
Build King Civil Engineering Limited
Description:
Reinforced Concrete for Common Utility Tunnel, Bridge, Underpass and Cycle Subway
Category of work:
RC works
Commencement date:
Aug 2022
Expected completion date:
Dec 2025
Contract value:
Approx. HKD 644,140,925

Contract 3310
Client:
China State Construction Engineering (Hong Kong) Ltd.
Description:
Formwork, Concreting, MJ Installation & Rebar Fixing and Drainage Works for Western Vehicular Tunnel (WVT)
Category of work:
RC works, drainage and road works
Commencement date:
Oct 2023
Expected completion date:
May 2025
Contract value:
Approx. HKD 434,555,100

Yuen Long South Development
Client:
CRECJV
Description:
Construction of Box Culvert BC06 & BC07 and Nullah Decking DC10 at Portion 16
Category of work:
RC works
Commencement date:
Dec 2024
Expected completion date:
Apr 2025
Contract value:
Approx. HKD 14,398,530